| Energy Desk | June 2026 | 4 min read |
| World Bank approves $300m additional financing for T4HP to cover T5HP cost overruns, as the 1,530MW Tarbela Fifth Extension nears its July 2027 commissioning target. |
| ⚡ QUICK TAKEAWAYS |
| • World Bank approved $300 million in additional financing for T4HP to cover cost overruns on the related T5HP project. |
| • T5HP — a 1,530MW powerhouse on Tunnel 5 of the Tarbela Reservoir — is at an advanced, ‘highly satisfactory’ construction stage. |
| • Commissioning of T5HP generation units is targeted for July 2027; the project is essential for the safe operation of Tunnel 5. |
| • Cost overruns stem from inflation, increased work quantities, gate replacement in Tunnel 5, and construction-period interest. |
| • T5HP is co-financed by AIIB ($300m) and WAPDA equity, alongside the original $390m IBRD loan processed under T4HP. |
The World Bank has approved an additional $300 million in financing for the Tarbela Fourth Extension Hydropower Project (T4HP), with the funds earmarked to cover cost overruns on the closely linked Tarbela Fifth Extension Hydropower Project (T5HP). The approval represents what officials describe as the final tranche of World Bank investment needed to deliver T5HP’s outcomes — a 1,530MW addition to one of Pakistan’s most critical pieces of water and power infrastructure.
| $300M New Financing final WB tranche for T5HP | 1,530MW T5HP Powerhouse Tunnel 5, Tarbela Reservoir | Jul 2027 Commissioning Target generation units |
Why T5HP Matters
T5HP is not simply an additional power generation project — it is tied directly to the structural safety of the Tarbela Reservoir, Pakistan’s most important infrastructure asset for both irrigation and electricity generation. Project documents state that completing T5HP is essential for the safe operation of Tunnel 5 at Tarbela. The project comprises a 1,530MW powerhouse and a raised intake in the existing Tunnel 5, alongside a 500kV double-circuit transmission line (T5TL) running from the T5HP switchyard to the Islamabad West Substation, with interconnections to other power plants in the Tarbela complex.
Construction of T5HP is described as being at an advanced stage with progress rated ‘highly satisfactory’. Commissioning of the generation units is targeted for July 2027. The hydropower component is being implemented by WAPDA, while the transmission line component (T5TL) is being executed by the National Grid Company, formerly the National Transmission and Despatch Company.
| 🏦 WHY T5HP IS FINANCED THROUGH T4HP Although T5HP finances entirely separate infrastructure from T4HP, its $390 million IBRD loan was structured as the first Additional Financing under T4HP — the ‘parent’ project. This is a common World Bank financing technique that allows a new project to be processed more quickly by attaching it to an existing, already-approved project framework rather than starting a fresh approval process from scratch. |
Why the Cost Overrun Happened
The additional financing was sought because civil works costs under the T5HP hydropower component have risen substantially. Four factors are cited: unprecedented inflation, higher-than-planned quantities of construction work, the need to replace and rehabilitate gates in Tunnel 5, and interest accrued during the construction period. Each of these factors reflects realities common to large infrastructure projects in Pakistan over the past several years — particularly the inflationary pressures that have affected construction costs across the economy.
The Financing Structure
| Financing Source | Amount | Loan / Credit ID | Status |
| IBRD Loan (T4HP original) | $400M | IBRD 81440 | Closed (June 2023) |
| IDA Credit (T4HP original) | SDR 283.7M | IDA 50790 | Closed (June 2023) |
| IBRD Loan (T5HP, as AF to T4HP) | $390M | IBRD 86460 | Extended to Sep 2027 |
| AIIB Co-financing (T5HP) | $300M | — | Extended to Jun 2028 |
| New Additional Financing (T4HP) | $300M | Pending | Just approved |
T4HP: The Completed Parent Project
T4HP itself is a completed and operational project, financing a 1,410MW powerhouse and modifications to Tunnels 3 and 4 of the Tarbela Reservoir. WAPDA was also the implementing agency for T4HP, which has been operational since 2018. The original World Bank financing for T4HP — a $400 million IBRD loan and SDR 283.7 million IDA credit, both approved on March 20, 2012 — have been fully disbursed and formally closed since June 2023.
T5HP, approved as Additional Financing under the T4HP umbrella on September 20, 2016, was also among the first World Bank projects in Pakistan to be co-financed alongside the Asian Infrastructure Investment Bank, with AIIB contributing $300 million approved on September 27, 2016. The closing date for the IBRD loan covering T5HP has been extended to September 30, 2027, while AIIB has extended its loan closing date to June 30, 2028 — both extensions aligning with the project’s revised commissioning timeline.
| 📋 WHAT ELSE THE LOAN COVERS Beyond the core construction, the IBRD loan also funds social and environmental management plans, construction supervision, impact evaluation, technical assistance, an Independent Panel of Experts (IPOE), a pilot floating solar project, and preparation of future projects — reflecting the World Bank’s standard practice of bundling safeguards and capacity-building into large infrastructure loans. |
Disclaimer: This article is based on reporting by Business Recorder and official World Bank project documentation. Loan amounts, identifiers, and closing dates are sourced from World Bank project records and are subject to revision.