Rawalpindi’s massive Rs. 35.28 billion road revamp is picking up speed, with a new Rs. 3.45 billion flyover announced for Ammar Shaheed Chowk to ease growing traffic pressure across the city.
What Is the Rawalpindi Infrastructure Overhaul?
Rawalpindi is undergoing one of its largest-ever infrastructure upgrades, backed by the Punjab government and spread across both city and cantonment areas. The package includes four flyovers and eight underpasses designed to unclog major intersections, reduce travel time, and improve safety for daily commuters.
The idea is to separate through traffic from local movement, remove long signal stops, and provide smoother links between key roads such as Adiala Road, Iftikhar Janjua Road, and other busy corridors. As the twin cities of Islamabad and Rawalpindi continue to grow, these projects are meant to keep traffic flowing instead of grinding to a halt at busy chowks.
New Flyover Announced at Ammar Shaheed Chowk
In the latest development, officials have approved an additional flyover at Ammar Shaheed Chowk after a sharp rise in traffic volume at the interchange. The new structure is estimated to cost Rs. 3.45 billion and is expected to start next year once final clearances are granted.
The Ammar Shaheed Chowk flyover will act as another key link in the wider network of projects, helping traffic move more smoothly between inner-city roads and cantonment areas. Planners hope it will reduce congestion, cut fuel wastage caused by idling, and make the junction safer for motorists and pedestrians.
Which Projects Have Already Been Completed?
So far, one major flyover and two underpasses under the package are already open to traffic. These include:
– The Nawaz Sharif Flyover at Khawaja Corporation Chowk, built at a cost of Rs. 4.4 billion
– GPO Chowk underpass
– TMA Chowk underpass, with both underpasses together costing around Rs. 5.7349 billion
These structures have started to ease pressure at some of the city’s busiest points, offering a preview of how the full project could transform Rawalpindi’s traffic once all components are finished.
Ongoing Flyovers and Underpasses Across the City
Work is currently in progress on two more flyovers and three underpasses at different locations. Construction on another three underpasses is scheduled to begin on 20 December, further widening the scale of the city’s road uplift.
At Kachehry Chowk, a combined flyover and underpass project launched on 3 November at a cost of Rs. 5.974249 billion is targeted for completion by 30 April 2026. A linked project at Jinnah Park, which includes a flyover and underpass worth Rs. 4.672245 billion, is expected to be completed by 30 March 2026.
Another important scheme is the underpass and road expansion on Iftikhar Janjua Road, worth Rs. 2.688073 billion, which is scheduled to finish by 30 January 2026. Adiala Road is also under redesign and expansion to handle heavier traffic volumes from new housing schemes and commercial activity.
What This Means for Daily Commuters
For residents of Rawalpindi and people who regularly travel between the twin cities, these projects promise long-term relief from daily traffic jams. Once the entire package is completed, commuters can expect:
– Faster movement through major junctions and chowks
– Fewer long queues at signals and crossings
– Safer travel with separate lanes and grade-separated flyovers
– Better connectivity between residential, commercial, and cantonment areas
However, until construction is complete, drivers should expect diversions, slowdowns, and temporary inconvenience near work sites. Authorities usually advise motorists to follow traffic plans, use alternate routes where possible, and allow extra time for travel.
Billions Being Invested in the City’s Future
With new flyovers, underpasses, and road expansions worth tens of billions of rupees, Rawalpindi is effectively redesigning its main traffic arteries for the next several decades. The addition of the Ammar Shaheed Chowk flyover shows that planners are also willing to adjust the plan as traffic patterns change on the ground.
If timelines are met and quality is maintained, the city could see a major improvement in mobility, fuel savings, and road safety. For now, the key challenge for authorities is to deliver all projects on schedule while managing construction-phase traffic in a way that keeps life moving for residents and businesses.