Energy & Resource | November 2026 | 3 min read
| Pakistan LNG Limited seeks two winter cargoes for Port Qasim in December and January. The reported $100 million per shipment is a market estimate. |
⚡ Quick Takeaways
- Pakistan LNG Limited invited international bids for two winter LNG shipments.
- The delivery windows are 14–16 December 2026 and 9–11 January 2027.
- Each cargo has a target volume of 140,000 cubic metres, with a 5% tolerance either way.
- Electronic bids are due by 2:00 p.m. Pakistan time on 6 November 2026.
- The reported estimate is about $100 million per cargo. The tender gives no final price.
Pakistan LNG Limited is seeking two shipments of liquefied natural gas for delivery to Port Qasim, Karachi, during the winter of 2026–27. The state-owned buyer has requested one December shipment and one January shipment as colder weather is expected to lift gas demand. At reported market prices, the two cargoes could cost about $200 million combined if purchased.
| 2 cargoes Winter shipments sought | 140,000 m³ Target volume per cargo | About $100 million Reported estimate per cargo |
When the winter LNG cargoes would reach Port Qasim
The Public Procurement Regulatory Authority published the invitation on 4 November. Pakistan LNG Limited, known as PLL, is seeking deliveries on a Delivered Ex-Ship basis. Under the tender, suppliers are bidding to bring the LNG by ship to Port Qasim during the requested dates. The windows tell suppliers when delivery is needed and help the buyer plan winter supplies.
Each shipment has a target of 140,000 cubic metres of LNG in liquid form. The permitted 5% variation means a cargo could range from 133,000 to 147,000 cubic metres under the tender terms. Together, the shipments have a nominal volume of 280,000 cubic metres. The requested dates and quantities would apply if PLL proceeds with the purchases.
| The tender sets delivery windows and target volumes. A contract award would confirm whether the shipments will go ahead. |
Tender dates and quantities at a glance
| Tender item | Timing or amount | Details |
| December cargo | 14–16 December 2026 | 140,000 m³ ±5% at Port Qasim |
| January cargo | 9–11 January 2027 | 140,000 m³ ±5% at Port Qasim |
| Bid deadline | 6 November, 2:00 p.m. | Electronic submission, Pakistan time |
| Bid opening | 6 November, 2:30 p.m. | Pakistan time |
PLL’s invitation is identified as PLL/IMP/LNGT80 in the reported bidding notice. Suppliers must file offers through version 2.0 of the E-Pak Acquisition and Disposal System. The public procurement listing shows that bids are due at 2:00 p.m. and scheduled to open at 2:30 p.m. on 6 November. It also identifies an accelerated procurement timetable for LNG to address a supply gap.
Why the cost is estimated at $100 million per shipment
ProPakistani estimated each cargo at about $100 million based on market prices. If both were bought at that level, the combined cost would be about $200 million. The tender notice does not list an agreed price. The actual amount will depend on the offers PLL receives and whether it accepts them after evaluation.
Spot LNG is bought for specific deliveries at prices available in the market around the time of purchase. Regional reporting placed an Asian spot price benchmark in late October near levels last seen in 2022. A benchmark gives a sense of market conditions. The amount a supplier bids for Port Qasim can also reflect freight, insurance and the timing of the requested delivery.
Why winter demand puts pressure on gas supplies
Households generally use more gas in colder weather for heating, hot water and cooking. The two requested deliveries are timed for December and January, when winter demand is expected to rise. Imported LNG must first be converted back into gas at a terminal before it can enter the distribution network. If a delivery slips, the gas from that shipment becomes available later than planned.
Additional cargoes could give the network more gas to allocate during the winter. The effect on supply in any particular area also depends on the rest of the import schedule, domestic production and how utilities distribute available gas. The next milestone is the bid opening. Any later award would clarify which cargoes PLL will buy and at what price.
Sources PPRA tender notice | Profit | ProPakistani | Independent Pakistan
Tender status and market estimates reflect information available on 5 November 2026.